Phase 1 - demolition and stabilization are finished. The building ends are nicely tarped off from further exposure to the weather.
The last of the environmental abatement was completed.
The brick and mortar strength testing has been performed.
Three elevator companies have been on site. The shaft is the only thing that can be saved according to all three companies. The general feeling is that a new elevator including shaft, in the long run, might be more cost effective.
Richard