Historic 701 offers several options and combinations of space in a setting unlike any other in Columbia. Whether you need to accommodate a crowd of 1000+ or entertain an intimate group of 20, 701 has a room or rooms for your event. 701 is perfect for weddings, receptions, art shows, formals, fundraisers, workshops or parties. We also have tables and Chiavari chairs for rent. For rates contact: Tom Chinn
803-771-0101 701whaley@gmail.com
701 LEASING OPPORTUNITIES
Retail/Restaurant Space available. Beautiful historic storefront perfect for restaurant, cafe, pub, small grocery or other retail. Contact: Tom Chinn
701 is a bit quiet on the outside but many things imperative to the development are happening.
Testing - this part is really eating up the clock but can not be avoided. We have had a total of three different pull out tests done to determine the strength of the brick and mortar.
Architecture - Robert and I have reviewed plans and elevations produced by Garvin. The upstairs floor plan is getting very close. The downstairs floor plan is largely open space and at this time we are positioning the floor plan to have some leeway to accommodate a variety of possible future tenants.
Phase 1 - demolition and stabilization are finished. The building ends are nicely tarped off from further exposure to the weather. The last of the environmental abatement was completed. The brick and mortar strength testing has been performed.
Three elevator companies have been on site. The shaft is the only thing that can be saved according to all three companies. The general feeling is that a new elevator including shaft, in the long run, might be more cost effective.
A task force was formed to help steer the use of 701 Whaley with two committees so far. For-profit and nonprofit. The vision for the nonprofit is to turn around 12,000sq ft of the upstairs into artist studio, gallery and administrative space. The non-profit now has an official name: 701 Center for Contemporary Art
There has been tremendous interest and things are moving fast. The nonprofit application process is underway and we are looking at grant opportunities.
I think some of the 2nd floor tenants will be getting a brand new floor & ceiling!
The for-profit direction has entertained lots of great ideas with a vision towards an event hall with complimentary retail for the downstairs.
We have entered 2007 with the expectation that 701 Whaley will be nearly full with occupants by years end. This is our main goal's target date and needs to be shared by everyone on the team as we race toward Spring...
The week between Christmas and New Years saw no activity on 701. This week the abatement contractor is alone in the building and should be wrapping up by weeks end. Other key items being worked on this week include architectural, structural engineering, and soil test preparations.
Hard target dates for key phases during the year are being refined.
Advisory committees for the building's use are being set up and we are excited about what the possibilities are. More to come on that soon!
Demolition and stabilization have started. Ummm. Excuse me Richard - but have you already gone towards the light? These guys are serious about preserving every savable inch of this historic building. Watch this video to see Richard on a mission.
Richard's Notes 12/15 We had a strong week at 701. I feel good about what has been accomplished and look forward to diving into next week.
This week at 701 - Week 3 - 12/18/06
Three main areas of work. 1. Floor and roof stabilization. I would estimate that this task is 90% complete and will be completed in the beginning of the week.
2. Demolition on the east side: a. Front - one last floor and roof section. b. Rear - one last roof section.
3. East exterior wall stabilization. This wall has been significantly weakened and a strong wind storm could bring it down. It will be reinforced until the new steel structure is put in place. Pole bracing will be erected at intervals on a diagonal both inside and outside of the building.
Some interesting finds for the week: An exterior entrance to the basement was discovered. An old stairwell (with no stairs) was found on the left rear. There is an area on the back right where you can see water in the basement. The reason became clear this week as to why - there is no floor. There used to be a floor - beam pockets can be seen.
Hood Construction should be wrapping up this first phase by the end of this next week. Hopefully our soil testing and engineering can proceed quickly so that Hood can start flying steel in during the early part of March.
Local ministers and neighbors gathered today to bless 701 Whaley. The prayer: "God whose word suffices to make all things holy, pour out your grace upon this building , so rich with past blessings, and grant that all who come and go through its doors might, with grateful heart and in keeping with your law and will receive from you, its Maker, health in body, protection of soul, and richness of your blessings now and in the days to come..."